How to price a bathroom renovation
A practical method for contractors: price from the scope, protect your margin, and give homeowners a number they can trust before you’ve set foot in the house.
Pricing · 8 minIn short: build every bathroom price from the same scope breakdown, add overhead and profit as margin (not as a habit markup), carry allowances and contingency openly, and give an early range by bathroom type. Confirm the final number after the site visit.
1. Start from scope, not from square feet
Square-foot pricing is tempting because it’s fast, but bathrooms don’t scale with floor area. A small bathroom with a walk-in shower, a niche and a new drain location can cost more than a larger one with a tub-to-tub replacement. What drives cost is the scope: what gets removed, what moves, and what gets built.
Break every bathroom into the same set of scope items, so each quote starts from a checklist instead of a blank page:
- Demolition and disposal: fixtures, tile, drywall, subfloor if needed, container or dump runs.
- Plumbing: rough-in changes, drain relocation, valves, fixture installation.
- Electrical: lighting, fan, outlets, heated floor connection, permit if required.
- Walls and floor prep: drywall or cement board, levelling, framing for niches and blocking.
- Waterproofing: membrane in the shower and wet areas. Never the place to save money.
- Tile: floor, shower walls, niche, trim, at the labour rate the format actually takes.
- Fixtures and finishes: vanity, toilet, shower system, glass, mirror, accessories.
- Finishing: paint, trim, caulking, cleaning, final walkthrough.
Price each item from your own numbers: your crew’s real hours, your trades’ real quotes, and your suppliers’ real prices. Generic cost data is a starting point at best. Your own past jobs are the most accurate database you have.
2. Know the decisions that actually move the price
Not every detail matters early. A towel bar or a new robe hook changes almost nothing. A handful of decisions change the price a lot, and they’re the ones to pin down first:
- Bathroom type: powder room, 3-piece, 4-piece or 5-piece.
- Layout: same layout, or moving the toilet, shower or vanity drain.
- Shower: tub, tub-shower, standard shower or walk-in with a linear drain.
- Tile: format and coverage. Large-format and floor-to-ceiling take more time.
- Vanity and fixtures: single or double, standard or floating, the fixture tier.
- Upgrades: heated floor, niche, bench, custom glass, lighting.
If you know these six things, you can give a useful range. Everything else can be confirmed at the consultation.
3. Markup is not margin
This is the most expensive mistake in renovation pricing. If your costs are $20,000 and you add 25%, you charge $25,000. But your margin, the share of the price you keep, is 20%, not 25%.
To hit a target margin, divide instead of multiplying: price = cost ÷ (1 − target margin). For a 30% margin on $20,000 of cost, that’s $20,000 ÷ 0.70 ≈ $28,571, not the $26,000 you’d get by adding 30%.
Your margin also has to pay for overhead before it becomes profit: the truck, insurance, your office time, the quotes you don’t win, and the site visits you do for free. Know your overhead per job, and make sure every quote covers it.
4. Carry allowances and contingency in the open
When the homeowner hasn’t chosen the vanity or the tile yet, use an allowance: a stated amount included in the price, adjusted up or down once they choose. Write the allowance amounts in the proposal so nobody is surprised.
For the unknowns behind the walls, such as rot, old plumbing or an uneven subfloor, decide how you handle them before you quote. Some contractors include a contingency line; others price the visible scope and handle the rest as written change orders. Either works, as long as the homeowner understands it before signing.
5. Give a range early, a firm price later
Homeowners want a number before they invite you over. Refusing to give one sends them to the contractor who will. A good compromise is to publish or share a range by bathroom type, adjusted by the big decisions above, and to confirm the final price after the site visit.
A range does two things: it filters out homeowners whose budget doesn’t match the project, and it anchors the conversation, so the final number doesn’t come as a shock. If your range is honest, most of your consultations will be with people who can afford the job.
6. Check the number before you send it
Before a price goes out, look at it the way you would after the job is done:
- Is every scope item from your checklist either priced or deliberately excluded?
- Is the margin on this job at or above your target, after overhead?
- Are the allowances and exclusions written in words the homeowner will understand?
- Would you be comfortable doing this job at this price if half the unknowns go wrong?
Key takeaways
- Price from a consistent scope breakdown, not square footage.
- Pin down the six decisions that move the price; leave the details for later.
- Set prices from target margin: cost ÷ (1 − margin).
- Write allowances, contingency and exclusions into the proposal.
- Share a range early, and confirm after the site visit.